Project Description

Construction of a 260 lineal m breakwater to protect Nova Scotia’s only all season fishing port in Digby, Nova Scotia. Over 350 000 tonnes of rock had to be drilled, blasted, loaded, hauled and placed into the ocean with tides as high as 31ft as it is part of the Bay of Fundy.

SCOPE INCLUDED:

  • Mobilization
  • Supply & Install Core
  • Supply & Install Filter
  • Supply & Install 1-2 Tonne Armour Rock
  • Supply & Install 2-4 Tonne Armour Rock
  • Supply & Install 4-6 Tonne Armour Rock
  • Supply & Install Cribs Ballasted
  • Supply & Install Granular Base
  • Site Clean-up