Project Description

At the CMM site:

  • Re-grading of the existing tailings area including waste rock within the tailings.
  • Demolition, transportation, and burial of concrete foundations.
  • Removal and recycling of scrap metal and mining equipment.
  • Drainage channel construction, placement of a soil cover, and revegetation.
  • Placement of deadfall and wooden/organic debris over the finished areas.

At the GT site:

  • Construction of a temporary access road from PR 314 to the tailings area.
  • Re-grading of the existing tailings area, drainage channel construction
  • Placement of a soil cover and revegetation over all disturbed areas.